ANTITERMITE
TREATMENT:
GENERAL :
Preconstructional anti-termite
treatment is a process in which soil treatment is applied to a building in
early
stages of its construction. The purpose
of antitermite treatment is to provide the building with a chemical barrier
against the sub-terranean termites.
Antitermite treatment being a
specialized job, calls for thorough knowledge of the chemicals, soils, termite
to
be dealt with and the environmental
conditions, in order to give effective treatment and lasting protection to the
property undergoing treatment. It is,
therefore, imperative that the works of antitermite treatment should be got
executed through specialized agencies
only. The specialized agency should be preferably a member of the
Indian Pest Control Association and
shall have sufficient experience of carrying out similar works of magnitude
envisaged in this tender.
The preconstructional soil treatment is
required to be applied during the construction stages of the sub-structure
upto plinth level. The contractor has
to be watchful of the various stages of sub-structure works and arrange to
carry
out the soil treatment in time after
proper co-ordination with Department and other contractors if any, working at
site.
SCOPE :
The scope of preconstructional
antitermite treatment covers the soil treatment with approved chemicals in
water
emulsion in foundation trenches for
columns, plinth beams, pile caps, brick walls, service trenches, lift pits,
steps,
ramps etc. in top surfaces of plinth
filling, at junction of walls and floor,in expansion joints etc. in stages as
detailed
in this specifications and drawings.
Unless otherwise stipulated, the antitermite treatment will be carried out as
per I.S.6313 (part II) 1981 and/or as
per direction of the Engineer-in-Charge.
SITE PREPARATION :
In order to ensure uniform distribution
of the chemical emulsion and to assist penetration, the following site
preparation shall be carried out:
a) Remove all trees, stumps, logs or
roots from the building site.
b) Remove all concrete form work if
left anywhere, levelling pegs, timber off-cuts and other builders debris from
the area to be treated.
c) If the soil to be treated is sandy
or porous, preliminary moistening will be required to fill capillary spaces in
soil in order to prevent the loss of
emulsion through piping or excessive percolations.
d) In the event of water logging of
foundation, the water shall be pumped out before application of chemical
emulsion and it should be applied only
when the soil is absorbent.
e) On clays and other heavy soils where
penetration is likely to be slow and on sloping sites, where run-off of
the treating solution is likely to
occur, the surface of the soil should be scarified to a depth of 75 mm.
atleast.
f) All sub-floor levelling and grading
should be completed, all cutting, trenches and excavations should be
completed with backfilling in place,
borrowed fill must be free from organic debris and shall be well compacted. If
this
is not done supplementary treatments
should be made to complete the barrier.
CHEMICAL TO BE USED :
The effectiveness of chemical depends
upon the choice of the chemical, the dosage adopted and the
thoroughness of application. The
chemical solutions or emulsions are required to be dispersed uniformly in the
soil
and to the required strength so as to
form an effective chemical barrier which is lethal and repellent to termites.
Soil Treatment : One of the approved
chemicals in water emulsion, recommended by the Indian Pest Control
Association (IPCA), and approved by the
Engineer-in-Charge, shall be used uniformly over the area to be treated.
The contractor should produce
voucher(s) for the chemical purchased and should get verified the sealed
container(s) of the specified chemical
from the Engineer-in-Charge before preparing the emulsion/use for the
treatment.
MODE AND RATE OF
APPLICATION :
The chemical emulsion as stated above
will be applied uniformly by sprayers at the prescribed rates as detailed
below in all the stages of the
treatment.
Treatment in
Foundation Trenches : In
case of normal wall load bearing structures, column pits, wall
trenches and basement, the treatment
shall be @ 5 ltrs./sqm. of surface area of the bottom and sides to a height
of atleast 300 mm. After the foundation
work, the sides shall be treated @ 7.5 ltrs./sqm. of vertical surface of
substructure on each side. After the
earth filling is done, treatment shall be done by rodding the earth at 150
mm. centers close to wall surface and
spraying the chemical with the above dose i.e. 7.5 ltrs./sqm.
DAE / DCSEM : 21 : SPN-CVL
In case of framed structure, the
treatment shall start at a depth of 500 mm. below ground level. From this depth
the backfill around the columns, beams
and R.C.C. basement walls shall be treated @ 7.5 ltrs./sqm. of the
vertical surface and @ 5 ltrs./sqm. for
the horizontal surface at the bottom in the trenches/pits.
Treatment on Top
Surfaces of Plinth Filling : The top surface of the filled earth within
plinth walls shall
be treated with chemical emulsion at
the rate of 5 litres/sqm. of the surface area before sub-base to floor is laid.
If
filled earth has been well rammed and
the surface does not allow the emulsion to seep through, holes upto 50 to
75mm. deep at 150 mm. centers both ways
shall be made with crow bars on the surface to facilitate saturation
of the soil with the emulsion.
Treatment at Junction
of Walls and Floors : Special
care shall be taken to establish continuity of the
vertical chemical barrier on the inner
wall surfaces from the finished ground level (or from level where the treatment
had stopped) upto the level of the
filled earth surface. To achieved this a small channel 30 x 30 mm. shall be
made
at all the junctions of wall/column
with floor (before laying sub-grade) and rod holes made in the channel upto the
finished ground level at 150 mm apart
and the iron rod moved backward and forward to break the earth and
chemical emulsion poured along the
channel @ 7.5 litres ( or at recommended quantity) per sqm. of the vertical
wall/column surfaces so as to soak the
soil right upto the bottom. The soil shall be tamped back into place after this
operation.
Treatment for
Expansion Joints : The
soil beneath the expansion joints shall receive special attention
when the treatment under 2.5.1 above is
in progress. This treatment shall be supplemented by treating through the
expansion joint after sub-grade has
been laid at the rate of 2 litres per metre length of expansion joint.
PRECAUTIONS DURING
TREATMENT :
a) Utmost care shall be taken to see
that the chemical barrier is complete and continuous. Each part of the area
shall receive the prescribed dosage of
chemical emulsion.
b) The treatment should not be carried
out when it is raining or when the soil is wet with rain or sub-soil water.
c) Once formed, the treated soil
barrier shall not be disturbed. If by chance, treated soil barriers are
disturbed,
immediate steps shall be taken to
restore the continuity and completeness of the barrier system.
PRECAUTIONS FOR HEALTH
HAZARDS AND SAFETY MEASURES :
All the chemicals mentioned above are
poisonous and hazardous to health. These chemicals can have an
adverse effect upon health when
absorbed through the skin, inhaled as vapours or spray mist or swallowed.
Persons
handling or using these chemicals
should be warned of these dangers and advised that absorption through the
skin is the most likely source of
accidental poisoning. They should be cautioned to observe carefully the
safety precautions given in 2.7.2 to
2.7.5 particularly when handling these chemicals in the form of
concentrates
These chemicals are usually brought to
the site in the form of emulsifiable concentrates. The containers
should be clearly labelled and should
be stored carefully so that children and pets cannot get at them. They should
be
kept securely closed.
Particular care should be taken to
prevent skin contact with concentrates. Prolonged exposure to dilute
emulsions should also be avoided. Workers
should wear clean clothing and should wash thoroughly with soap and
water specially before eating and
smoking. In the event of severe contamination, clothing should be removed at
once
and the skin washed with soap and
water. If chemicals splash into the eyes they shall be flushed with plenty of
soap
and water and immediate medical
attention should be sought.
The concentrates are oil solutions and
present a fire hazard owing to the use of petroleum solvents.
Flames should not be allowed during mixing.
Care should be taken in the application
of chemicals/soil-toxicants to see that they are not
allowed to contaminate wells or springs
which serve as source of drinking water.
GUARANTEE :
The contractor has to furnish the
guarantee for 10 (ten) years from the date of completion of work, stating that
in
case of reappearance of termites within
the building area due to defective materials or workmanship or due to any
other reasons, the contractor will
carry out the necessary post constructional treatment to keep the entire area
free
from termite, once again, without any
extra cost to the Department during the guarantee period.
MODE OF MEASUREMENT :
The payment will be made on the basis
of plinth area measurements at ground floor only for all the stages of
treatment
in sqm. correct to two places of
decimals. Rate includes the cost of materials, labour and all tools,plants,
sprayers required for complete operation.